LA Weekly has published an article about the 16th St Outpatient Services Building.
Open this link, then Click Here to read the article.
December 28, 2012
LA Weekly has published an article about the 16th St Outpatient Services Building.
Open this link, then Click Here to read the article.
September 06, 2012
Architectural Record has published an article about the 16th St Outpatient Services Building.
Open this link, then Click Here to read the article.
December 01, 2011
A Letter of Intent between Nautilus Group and an investment partner was signed on September 28, 2011 for a private student housing project in Berkeley, CA.
Nautilus Group will perform all services for the project including entitlement, design, permitting, financing, construction and leasing. We have already begun conceptual design.
The project, located just 3 blocks south of UC Berkeley, may feature a modular construction system and automated parking similar to the system installed at the 16th Street, Santa Monica project. The preliminary design contemplates approximately 95,000 square feet of student housing and over 300 beds.
While the design phase of the project is expected to take a bit longer than a conventional ‘sticks & bricks’ type project due to the modular construction design, the construction phase of the project is expected to be delivered in approximately 8 mos. as opposed to 14-18 mos. for conventional construction. To get an idea of what modular construction is, check this out – Modular Construction Example Video. Pretty cool, right? We think so too. Some folks were skeptical when we decided to do a custom, fully automated parking system on our 16th St Project, but we’re happy to report that the system is in the midst of final testing and all is well.
We are also pleased to announce that our Northern California office will open in the San Francisco Bay Area in December of this year. We are continuing to pursue projects in Southern California and a few other select cities. Stay tuned.
November 28, 2011
Construction is wrapping up at the UCLA Sixteenth Street Outpatient Services Building. The i’s are being dotted and the t’s are being crossed.
Equipment and building systems start-up is underway and commissioning is commencing today, 11/28. The automated parking system has successfully parked and retrieved vehicles and fine tuning of the software and laser equipment is scheduled for completion 12/1. We anticipate Substantial Completion for the project on 12/15.
In terms of completion percentages by cost, the core and shell work and the interior improvements are both approximately 99% complete.
Our next update will likely include professional photos of the completed project. In the meantime, please enjoy the recent progress photos below.
November 16, 2011
KCRW radio aired an interview with our President, Randy Miller, about the fully automated parking system at our 16th St Outpatient Service Building project.
Open the link below to listen to the interview.
November 16, 2011
LABJ (Los Angeles Business Journal) has published an article about the 16th St Outpatient Services Building’s Automated Parking System.
Open this link, then Click Here to read the article.
November 11, 2011
Healthcare Design Magazine has published an article about our 2011 AIA National Healthcare Design Award.
Open this link, then Click Here to read the article.
September 03, 2011
Construction continues on pace at the UCLA Sixteenth Street Outpatient Services Building. It has been a busy & productive month since our last update.
Finishes in the building are well underway; Painting, flooring, tile, cabinets & counter tops, ceilings, interior glazing, doors & hardware are all hitting the floors at a good clip.
The atrium bridges and ‘gravity defying’ floating stairs are taking on their final form and the walls are being prepared for bamboo wood panels.
The linear accelerator vault which is used for oncology treatment is taking form. The walls and flooring will have a beautiful bamboo finish. The patients will be unaware of the 42″ thick concrete, 7″ thick lead and a 14,000 lb. door that surrounds them and protects the adjacent spaces from the linear accelerator particles.
Medical equipment vendor have begun installation in the building. Medical gas & light booms have been installed in the 8 operating rooms. Headwalls have been installed at most of the 24 prep & recovery bays.
3 large HVAC package units were delivered and set on the roof with a 280-ton crane.
Miles… and miles… and miles of Cat6 data cabling has been pulled throughout the building and over 1,100 terminations will be completed at the server racks in the next 3 weeks.
The site walls and concrete flatwork in the front yard are well underway. Landscaping will commence in about 2 weeks.
AND… last, but not least… our 100kw solar array that covers about 75% of our roof (and actually cantilevers past the edge of the roof in areas) is complete.
Our daily manpower has averaged about 95 workers per day this month.
In terms of completion percentages by cost, the shell and core work is approximately 94% complete and the interior improvements are now about 78% complete. We are on track to complete construction by October. Commissioning of building systems, training and turnover are currently scheduled in early November.
July 22, 2011
Construction continues on pace at the UCLA Sixteenth Street Outpatient Services Building.
Interior partition framing and drywall is close to 100% complete on all floors and the focus has shifted overhead to ceilings. Ceiling grid has started on the 3rd floor and will continue to the lower floors. Finishes have started on the 3rd floor including paint, casework and tile is scheduled to start Monday, 7/25.
Our ‘gravity defying’, floating stair in the atrium is in place and the temporary support posts have been removed.
We began excavation of our common trench which crosses 16th Street and connects to the UCLA Orthopedic Hospital on July 6th. The common trench which is 240 feet long connects the two facilities with data conduits, high pressure steam and a pneumatic tube system. The high pressure steam line will be connected to the central plant at the Hospital and will serve heating hot water and doemestic hot water in our building and will also provide steam to serve the sterilizers and cart washers for cleaning the medical equipment. The pneumatic tube system will enable the staff to send canisters of lab specimens and paperwork via the high speed tube system between the two facilities which are separated by 16th Street. The trench work is scheduled to be complete at the beginning of August.
Our Automated Parking System is progressing nicely and is on schedule. The cranes are assembled and have been connected to temporary power to test the movement. Tuning of the motors, software programming and laser installation will begin soon.
Our daily manpower has averaged about 95 workers per day this month.
In terms of completion percentages by cost, the shell and core work is approximately 90% complete and the interior improvements are now about 60% complete. We are on track to complete construction by October.
May 24, 2011
Construction continues on pace at the UCLA Sixteenth Street Outpatient Services Building.
Interior partition framing is approximately 90% complete and the 1st side on drywall has started on the 2nd and 3rd floors . Plumbers have completed approximately 40% of their plumbing and approximately 25% of HVAC is complete. Electrical progress is following closely behind plumbing and HVAC. All in-wall plumbing and electrical work will be complete by the end of the month. The roofing installation is complete. Our daily manpower has averaged about 75 workers per day this month.
In terms of completion percentages by cost, the shell and core work is approximately 80% complete and the interior improvements are now about 36% complete. We are on track to complete construction by October.
On May 17th, we received delivery of the Automated Parking Cranes which arrived on flat beds from Michigan. The pieces of the large cranes were hoisted into the 6 level subterranean parking vault with a 240-ton crane. Here are a few shots from the hoisting activities:

240-ton crane is preparing to hoist a 50 foot section of the automated parking crane into the building.

The 50 foot section was lowered slowly through a hatch opening in the grade level deck and down to the parking vault pit level about 50 feet below grade.

The first large section of the automated parking crane is lowered into the parking vault 50 feet below grade.

With all the large pieces hoisted into the parking vault, erection of the cranes has begun at a good pace. The automated parking cranes are scheduled for commissioning and final testing in August of this year.