Construction continues on pace at the UCLA Sixteenth Street Outpatient Services Building. It has been a busy & productive month since our last update.

North Wing, West Elevation (Click to Enlarge)
Finishes in the building are well underway; Painting, flooring, tile, cabinets & counter tops, ceilings, interior glazing, doors & hardware are all hitting the floors at a good clip.

Millwork in the 3rd Floor Waiting Rooms (Click to Enlarge)
The atrium bridges and ‘gravity defying’ floating stairs are taking on their final form and the walls are being prepared for bamboo wood panels.

Click to Enlarge
The linear accelerator vault which is used for oncology treatment is taking form. The walls and flooring will have a beautiful bamboo finish. The patients will be unaware of the 42″ thick concrete, 7″ thick lead and a 14,000 lb. door that surrounds them and protects the adjacent spaces from the linear accelerator particles.

Linear Accelerator Vault (Click to Enlarge)
Medical equipment vendor have begun installation in the building. Medical gas & light booms have been installed in the 8 operating rooms. Headwalls have been installed at most of the 24 prep & recovery bays.

Operating Rooms with Booms Installed (Click to Enlarge)
3 large HVAC package units were delivered and set on the roof with a 280-ton crane.

1 of 3 HVAC Package Units Ready to be Hoisted to the Roof (Click to Enlarge)

Package Unit Being Hoisted to the Roof (Click to Enlarge)
Miles… and miles… and miles of Cat6 data cabling has been pulled throughout the building and over 1,100 terminations will be completed at the server racks in the next 3 weeks.

Cat6 Data Cable Prior to Terminations at Server Racks (Click to Enlarge)
The site walls and concrete flatwork in the front yard are well underway. Landscaping will commence in about 2 weeks.

Site Walls are Formed & Scheduled to be Placed on 9/6 (Click to Enlarge)

Patio Concrete Mock-Up. Accent Areas Will be Stained White & Sealed (Click to Enlarge)
AND… last, but not least… our 100kw solar array that covers about 75% of our roof (and actually cantilevers past the edge of the roof in areas) is complete.

Our daily manpower has averaged about 95 workers per day this month.
In terms of completion percentages by cost, the shell and core work is approximately 94% complete and the interior improvements are now about 78% complete. We are on track to complete construction by October. Commissioning of building systems, training and turnover are currently scheduled in early November.